Hanjin Main Gate Complex Pier A, Port of Long Beach

Sacramento
$21 Million

Construction of the main gate complex for Hanjin Shipping to include a three-story, steel framed administration building, concrete and block driver service building, concrete and steel frame recieving and delivery canopy, concrete and steel frame security building, concrete transfer dock, block generator enclosure, concrete and steel frame sign bridge, concrete and steel frame trellis, eight truck scales and concrete islands, truck entrance intercom system including pedestals and scale interface, inspection canopy, two gaurd buildings and eight clerk booths. This project was expanded to include the secondary gate complex which was similar to the above.

Start: January 1997
Completion: September 1997