Porterville Developmental Center

Porterville
$3.2 Million

Design and installation of a new 2,400 ton capacity chilled water cooling system for the existing facility. The work includes installation of new chillers and cooling towers, electrical switchgear and transformers and underground piping connections to 34 buildings. The work also includes the installation of a complete new computerized control system for the entire campus.

Start: November 2002
Completion: May 2003

 
.
.